Three Mine Geological Environment Restoration and Treatment and Supervision Procurement Project

12/27/2021 3:02:01 PM

The project is invested by the Natural Resources Bureau of Zhangqiu District, Jinan City. Our company undertakes the construction of treatment measures such as risk elimination, backfilling slope, rough stone retaining wall, planting soil backfill, site cleaning, greening, etc., including risk elimination of about 23,000 ㎡, backfill of slope about 36,000㎡, construction of rough stone retaining wall about 1,500 m³, backfill of planting soil about 10,000m³, site clearance about 35,000㎡, planted 1,461 forsythias, 2,107 Chinese arborvitae, 864 locusts, 2,673 Boston ivy.

The project is based on the principle of controlling the geological environment of the mine, reducing the exposed surface and visual pollution of rocks, increasing the vegetation coverage of damaged mountain, carrying out site ecological restoration, adopting engineering means for upright slopes and slope bottoms, building plant living environments by eliminating risks, backfilling slopes, building retaining walls, planting soil backfilling, etc., and then covering the cliff walls through greening planting.

The project began construction on November 23, 2020 and the completion and acceptance was completed on May 20, 2021, which lasted 179 days. The quality of the project is qualified, and there were no safety accidents and no damage to the environment during the entire construction process.

After the construction of this project, the appearance of the site has changed dramatically, not only eliminating the hidden danger of crumbling geological hazards, but also playing a positive role in improving the level of local habitat and promoting social harmony.

Add:NO.555 Huaian Road(west),Shijiazhuang City,Hebei Prov. P.C.:0502271   Tel:0311-66723100 66723200 Fax:0311-66723277  
Copy right:China Hebei Construction & Geotechnical Investigation Group Ltd. 2008
Baidu
sogou