The project is located in Xing County, Lvliang City, Shanxi Province. The project is invested by Shanxi Jinxing Energy Co., Ltd., Our company is responsible for the site leveling construction of the project, including about 1.5 million cubic meters of site leveling soil, about 680 cubic meters of ditch (tunnel) construction, and about 13,000 square meters of laying plastic film for side slope protection.
Construction began on October 25, 2015 and was completed on November 20, 2021. In the whole construction process, in the face of poor soil quality, tight construction period, poor construction conditions and other unfavorable factors at the construction site, our project department strictly followed the unified coordination and arrangement of the owner, scientifically organized, carefully deployed, in strict accordance with the construction technology steps and measures, implemented safety and quality at all levels. Under the unremitting efforts of all project personnel, the nodal target of the owner was completed in quality and quantity.
During the construction process, our project department cooperated with the testing unit to test each layer of backfill soil, and the test results were qualified. During the construction period, the owner and the supervision unit sent engineers to supervise on the spot, and we strictly abided by relevant laws and regulations, various standards and norms in the process, conscientiously performed the contract, from the start to the completion, no safety and quality accidents occurred. which won the unanimous approval and praise from the owner and related departments.